Territory Stories

2015/2016 Standard specification for road maintenance

Details:

Title

2015/2016 Standard specification for road maintenance

Collection

Standard specification for road maintenance; Reports; PublicationNT

Date

2015

Description

Made available via the Publications (Legal Deposit) Act 2004 (NT).

Language

English

Subject

Roads -- Northern Territory -- Maintenance and Repairs -- Periodicals

Publisher name

Department of Infrastructure

Place of publication

Palmerston

Copyright owner

Check within Publication or with content Publisher.

Parent handle

https://hdl.handle.net/10070/305186

Citation address

https://hdl.handle.net/10070/360778

Page content

TRAFFIC SIGNALS AND INTELLIGENT TRANSPORT SYSTEMS MAINTENANCE STANDARD SPECIFICATION FOR ROAD MAINTENANCE DoI REFERENCE TEXT October 2015 Page 168 Table 16.12 - Response Times MAINTENANCE OR ACTIVITY ALARM TYPE TIME FOR ATTENDANCE / RESPONSE BRIEF REQUIREMENTS refer to Maintenance Section & Measurement & Payment for further details Legend for SCATS related alarms: BO: Black Out DA: Detector Alarm FY: Flashing Yellow LF: Lamp Fault NC/DZ/ST: SCATS Communications fault related PB: Pedestrian Button Detector Alarm WD: Watchdog NOTE: All response times listed are inclusive of after hours, weekends and public holidays all response times apply NOTE: Maintenance & timeframes identified as urgent is entirely at the discretion of the Superintendents Rep, DoI Traffic Section, or On Call staff. Maintenance identified as urgent may be based on high risk consideration (danger to the public or workers), maintenance required prior to peak hours, or other urgent requirements. Detector Fault DA 2 Hours The provision of time for the contractors technician to be onsite, appropriately equipped to test & repair all components of a faulty traffic signal vehicle detector. Detector Recut / Installation DA 7 Days The provision of time for the contractors technicians to be onsite, appropriately equipped to arrange & install or recut a traffic signal vehicle detector. Pedestrian Push Button Repair or Replacement (including audio) DA / PB 2 Hours The provision of time for the contractors technician to be onsite, appropriately equipped to test, repair or replace all components of a faulty traffic signal pedestrian push button, including all audio tactile components. Communications Test & Restore Traffic Signals or ITS NC / ST / DZ TSC - 2 Hours ITS 24 Hours The provision of time for the contractors technician to be onsite, appropriately equipped to test, repair or replace all components of faulty communication equipment for traffic signals or ITS equipment. Specific Maintenance Site Audit Vehicle Signalised Intersection - 7 Days The required time for a physical audit to be fully arranged, completed & recorded. Site Audit Pedestrian Signalised Crossing - 7 Days The required time for a physical audit to be fully arranged, completed & recorded. Site Audit Completed Report - 7 Days The required time for the final audit report, drawing/s & quotes to be submitted & accepted by DoI Traffic Section. UPS Maintenance & Report - 7 Days The required time for the physical inspection & testing to be completed, & the corresponding report to be completed & submitted to DoI Traffic Section.


Aboriginal and Torres Strait Islander people are advised that this website may contain the names, voices and images of people who have died, as well as other culturally sensitive content. Please be aware that some collection items may use outdated phrases or words which reflect the attitude of the creator at the time, and are now considered offensive.

We use temporary cookies on this site to provide functionality.
By continuing to use this site without changing your settings, you consent to our use of cookies.