Technical Report WRD85068 Viewed at 15:07:30 on 29/07/2010 Page 7 of 58. I I I I I I I I I I I I I I I I I I I I 3.0 SUMMARY OF CONCLUSIONS AND RECOMMENDATIONS The report calls for new works to be undertaken in the following three stages (all values in 1985 dollars) : Stage 1. Immediate program to correct deficiencies. Estimated Cost $62000 Stage 2. To be carried out in conjunction with construction of new storage tank and pump station. Estimated Cost $619000 Stage 3. As required by continued monitoring of the system. Estimated Cost $129000 3